The Board approved Pay Application #1 for Hadar West (Project #221896) for $121,387.98 to Theisen Construction, approved a 5.32‑acre lot split for Gary R. Ronspies, and audited and allowed multiple claims across county funds including payroll disbursements.
The full story
Pierce County commissioners on Sept. 29 approved several operational and land‑use items, including a construction pay application, a private lot split and the routine audit of claims.
The board approved Pay Application #1 for the Hadar West / JEO Project #221896, payable to Theisen Construction, in the amount of $121,387.98. The motion carried on unanimous roll call. Commissioners also approved the Gary R. Ronspies lot split (5.32 acres in part of the SW 1/4 SW 1/4 of Section 27, Township 27 North, Range 1 West) after a presentation by Zoning Administrator Heather McWhorter and applicant Gary Ronspies.
The board moved to audit and allow claims across multiple funds. The minutes list detailed disbursements in the General Fund (including payroll of $67,396.83), County Highway Fund (including payroll of $36,771.89 and a $24,606.54 payment to Bazile Aggregate Co.), and smaller entries in Visitor Promo, Register of Deeds, Inheritance, 911 and 911 Wireless funds. The board approved the claims and instructed the County Clerk to issue checks for payment.