Commission approves Farm Center change orders reducing contract and certifies courthouse substantial completion
Jul 14, 2025
Jul 14, 2025
The Commission approved five change orders that reduced the Farm Center renovation contract by $53,866.02 (final $2,517,391.98) and authorized the chairman to sign; it also approved resolution authorizing signature on the certificate of substantial completion for the Courthouse renovation.
The full story
County Attorney Phil Eldridge told the Commission the Farm Center renovation had five approved change orders from the OAC meeting that decreased the contract price by $53,866.02, reducing the total from $2,571,258.00 to a final $2,517,391.98. Commissioner Weston Spivey moved to approve the change orders and allow Chairman Toby Seay to sign; Commissioner Jeff Hatcher seconded and the motion carried 3-0.