Nutter Run Complete; Chub Run Sewer and Phase II AML Move Forward
Jul 28, 2026
Council heard that the Nutter Run Project is complete pending sample testing, Chub Run sewer work is progressing and will be synchronized with a new wastewater treatment plant, and Phase II AML pre-bid was scheduled for 8/20 with bid opening 9/8 (possibly 9/10) to reroute acid mine drainage behind Food Lion and along Buckhannon Pike.
The full story
Council received several engineering updates. Officials reported the Nutter Run Project is complete and that water-quality samples will be taken Thursday before placing the system into service if tests are satisfactory. The Chub Run sewer project is progressing; staff said its timeline is interdependent with a wastewater treatment plant on the opposite side of the interstate and that a contractor time extension is being processed to synchronize activation.