During Phase 1 of the CTH U storm sewer work crews discovered an undocumented existing storm sewer that appears to have a collapsed section; television footage reached 208 feet then 85 feet to a manhole in the mill yard before the camera became stuck at a 45‑degree bend.
The full story
Public Works Director Kayla Lumaye reported that most of the Phase 1 storm sewer installation for the CTH U project is complete. While testing the connection at new manhole 1.4, crews discovered an undocumented existing storm sewer that has historically contributed to flooding near North and South Biron Drive.