Greeneview Local outlines timeline for partial elementary roof replacement

Oct 15, 2026

District architects completed thermographic scans and pull tests for the elementary-school roof and the board was given a tentative procurement timeline: Oct. 22 meeting with Shore Architects, advertise bids Nov. 5, pre-bid meeting around Nov. 12, and target contractor selection by the Dec. 17 board meeting.

The full story

Superintendent told the board that Shore Architects completed thermographic scans and pull tests for the elementary-school roof and reported no unexpected concerns about the partial replacement scope. He said staff are scheduled to meet Shore Architects Oct. 22 to review the scans and construction documents.