Lyons SD2 discusses SCADA upgrade; board questions Starlink and FirstNet options
Apr 21, 2026
Apr 21, 2026
District staff reported progress on a SCADA upgrade and the board queried alternative communications options including Starlink and FirstNet. Board members and staff also discussed a TDML proposal and suggested challenging WDNR and legislators before the first permit is issued.
The full story
District staff provided a progress update on the SCADA (Supervisory Control and Data Acquisition) upgrade during the April 21 meeting. Jim DeLuca asked whether contractor CPME had considered using Starlink for communications and whether the district should retain the existing inductive automation SCADA; he also asked if FirstNet is a constraint on the communications choice.