Trustees reject feasibility study to replace Gebhardt DPW building
Sep 8, 2026
The Village of Warrens board voted 0-6 against moving forward with a feasibility study to evaluate replacing the Gebhardt Department of Public Works building; trustees discussed options but declined to fund the study at this meeting.
The full story
Trustee A. Werner moved and P. Hardiman seconded a motion to proceed with a feasibility study assessing options for the Gebhardt Department of Public Works building, including renovation versus new construction. The board recorded the motion as failed, vote total 0-6.
DPW Director Brian Knoepker had presented the second engineer's review and outlined options for updating the existing facility or constructing a new building. The minutes note the proposed feasibility study and associated cost were discussed but do not specify the amount. No follow-up funding or timeline was approved at the meeting.
Written with AI from the event video and transcript. Check it against the source ↓