Commissioners split 2-1 on Gilbane storage contingency; motion fails
Oct 16, 2026
The board voted down a construction-manager contingency request from Gilbane to store a pre-engineered metal building for the Social Services Administration Facility after two commissioners said the contractor should absorb the cost; vote was Merrill yes, Lewis and Benton no.
The full story
Facilities director John Melvin explained the contingency request for storage of a pre-engineered metal building and said staff recommends approving the use of construction-manager contingency funds to cover the cost after schedule delays and GMP timing changes. Pizzuti representatives said delays and cost escalation drove a need for storage authorization.