Board reviews gatehouse and monument renovation plan; CIP changes may require roughly $2.5M loan
Apr 28, 2026
Apr 28, 2026
The Board reviewed a revised long-range plan that includes gatehouse and monument replacements, a $291,500 backup irrigation well near completion, and CIP changes that Mr. Adams said will necessitate an approximate $2.5 million loan; permitting to the Village of Estero and SFWMD coordination were discussed.
The full story
The Board reviewed a revised Long Range Plan for Pelican Sound gatehouses and neighborhood monuments, including cost estimates, permitting steps and timing. Eric Long, PSGRC General Manager, noted estimated probable costs: monument replacements at approximately $250,000, gatehouse renovations estimated at $615,775 for FY2026 and $407,240 for FY2027, and Phase III paver work budgeted at $125,000 for work around the main gate.