Board closes hearing, directs decision drafting on Patton Crossing drive‑throughs

Aug 19, 2026

Patton Township held a public hearing on a conditional use for Patton Crossing Phase 2C—a 7,482 sq ft bank and a 3,000 sq ft restaurant with a drive‑through—and directed staff to prepare Findings of Fact and a written decision for the Sept. 9 meeting after attaching recommended conditions.

The full story

The Patton Township Board of Supervisors closed a public hearing Aug. 19 on a conditional use application for Patton Crossing Phase 2C and directed the Township Manager to prepare Findings of Fact and a written decision for consideration at the Sept. 9 regular meeting.

Staff said the application, submitted on behalf of 1752 North Atherton Street Associates LP, proposes a 7,482‑square‑foot bank and a 3,000‑square‑foot fast‑casual restaurant with a full‑service drive‑through and dual order points on the northwest corner of Phase 2 of the 28.486‑acre Patton Crossing development. Staff recommended conditions intended to reduce pedestrian and vehicle conflicts, including placing a crosswalk at the Cava dumpster location, signage indicating Roxbury Street is right‑turn only from Meridian Street, limiting directional signs on site to five square feet with no advertising icons, exploring internal traffic control measures, and completing a post‑construction stacking and queuing analysis within six months of opening.

During the hearing Ms. Kruesi asked about the purpose of the crosswalk; Tony Fruchtl of Penn Terra Engineering said the crosswalk is intended to provide employees access to the refuse/recycling area. The Board voted 4–0 to close the public hearing and, in a separate motion that passed 4–0, to direct the Township Manager to bring written Findings of Fact and a draft decision to the Sept. 9 meeting for formal action.

The conditional‑use approval would not itself authorize building permits or a land‑development plan; staff noted it is one step in the overall development review process and that additional permits and reviews are required before construction.