Contractors give timeline for Lytle elevated water storage tank; substantial completion expected Nov. 20
Aug 24, 2026
Aug 24, 2026
Project engineer and contractor representatives reported painting nearly complete, remaining site work and electrical scheduled over coming months, and a substantial completion date of Nov. 20, 2026; council discussed inspection and sample-pulling responsibilities.
The full story
Scott Horowitz, project engineer of record for the elevated water tank, told the council the painting is nearly finished and that "the project overall has a substantial completion final of November 20th." He said final site work, electrical work and tank filling would take place over the next three months.