Secretary Jay Stuttgen, reporting for OIC Kyle Parks, said phosphorus levels meet Department of Natural Resources limits but that retaining the current phosphorus-control system would require an operator with Advanced certification; Kyle will correct paperwork and prepare three system proposals if the current system is removed.

The full story

Secretary Jay Stuttgen, reading the operator-in-charge report on behalf of Kyle Parks, said, "Current phosphorus levels are within our DNR limits." Jay told the board that, per DNR guidance, "to keep current phosphorus system, the OIC will need to have Advanced certification." The statement flags a staffing and compliance choice that could affect who can operate the plant.