Project team: program estimate at $255M; county target and financing leave limited wiggle room

Oct 16, 2026

Project leadership presented a new contractor estimate at about $255 million while saying the county’s program financing and bonding plan can absorb higher costs, and urged boards to prioritize value-engineering choices at a Nov. 19 follow-up meeting.

The full story

Project managers told the Airport Advisory Board and the Board of County Commissioners on Oct. 15 that the airport modernization program is now carrying a substantially higher estimate than the $191 million construction target set last year. Carter, the county’s project manager, said the program has recalibrated toward a $210 million construction target and that a contractor estimate now sits at about $255 million.