Downtown construction progressing; signal work, parking adjustments expected
Oct 14, 2026
City staff reported that mainline concrete work is complete and crews will begin signal bases and driveway tie‑ins after Farm City Days; staff warned of temporary parking impacts and said KDOT funding limits mean businesses may cover some additional costs for feasibility requests.
The full story
Staff reported progress on a downtown highway project: mainline concrete has been poured and the next steps include curb and driveway tie‑ins and installation of signal bases after Farm City Days.
"They finished pouring mainline today," staff said, and noted that underground work for traffic signals is in place and that signal bases and related work should begin after the holiday events. Staff also described a requested design change from a business (Bettis) to improve employee access; staff said the city will consider feasibility if the change does not increase costs to the city since KDOT funds are limited.
Council acknowledged the construction inconvenience and encouraged businesses and residents to be patient; staff said alternative parking options exist within a block or two and that work is expected to proceed in phases over the coming weeks. The update did not require formal council action.
Written with AI from the event video and transcript. Check it against the source ↓