Technology Services reports 99.5% July availability; phone system and camera upgrades underway
Aug 15, 2024
Aug 15, 2024
Marinette County Technology Services reported July network availability of 99.5% and listed ongoing projects including phone system router installs, imaging migration off old SAN devices, an O365 migration delayed by MDM vendor issues, security camera upgrades, and planned Camp Bird Wi‑Fi and redundant firewall work slated for 2025.
The full story
Technology Services Director Kevin Solway presented the department’s August report (Exhibit A) to the Administrative Committee on Aug. 15. The report lists operational work and multi-vendor coordination for several projects: