Engineer gives Merrimac Bridge timeline as commission holds funds set aside

Jan 10, 2025

Lead engineer Pete Schierloh updated WRRTC on Merrimac Bridge design and schedule; the treasurer reported $270,735 held in LGIP for the bridge and a recent large payment to the project was recorded in October financials.

The full story

Pete Schierloh, the primary engineer for the Merrimac Bridge design (SW Bridge), presented a timeline and status update to the Wisconsin River Rail Transit Commission at its Dec. 6 meeting, summarizing current engineering progress and schedule expectations.