Park Ridge gets construction update; trustees approve Pay Application No. 2 for Hillcrest/Greenbriar project

Oct 20, 2025

Contractor A-1 Excavating has finished underground work and roughly 80% of gravel placement; trustees approved Pay Application No. 2, noted as covering about 52% of project cost though progress estimated at 80%; substantial completion scheduled Oct. 28 and final by Nov. 11.

The full story

Tom Turchi of engineering firm MSA presented the Hillcrest Drive/Greenbriar Avenue construction update. He said A-1 Excavating has completed all underground work, Van Ert installed conduit and wiring and the base for a new cabinet is in place, and American Asphalt planned fine grading and binder placement later in the week. Turchi reported "approximately 80% of the gravel has been placed" and that nine manhole covers will be set using the contractor's "Mr. Manhole" process; Van Ert is awaiting delivery of nine light poles expected by Nov. 6.