Park Ridge hears Hillcrest/Greenbriar project update, approves $371,276 contractor payment
Sep 15, 2025
MSA reported grading, conduit and water-main progress on the Hillcrest Drive/Greenbriar Avenue reconstruction; the board approved Pay Application No. 1 for $371,276.15 and reviewed change orders, a Hillcrest extension estimate and a pavement-thickness adjustment that slightly increased the project budget.
The full story
MSA engineer Tom Turchi reported progress on the Hillcrest Drive/Greenbriar Avenue road reconstruction and said the project remains on schedule despite a few days' delay in grading. "A-1 Excavating plans to have their grading crew back on site this Wednesday to continue grading operations," Turchi said. He added that water-main installation and service laterals were completed approximately one week ahead of schedule and that homeowners may now connect to the new mains.