Trappe approves Lakeside sludge removal application; developer to bear costs
Mar 5, 2025
Mar 5, 2025
Council unanimously approved a permit application allowing sludge from the Lakeside plant to be hauled to Easton Utilities; the Town and Trappe East must both appear on the discharge permit and the developer is financially responsible for costs.
The full story
James Cook of Rauch told the council that sludge from the Lakeside wastewater plant must be hauled out every six to eight months to Easton Utilities and that the Town's existing permit allows hauling from Easton to Trappe but not the reverse. He said a permit application has been submitted to allow hauling from Trappe to Easton, and that because both entities are on the discharge permit, the permit must list both the Town and Trappe East.