Commission requests additional quotes to replace Lift Station 2 pump installed in 2003
Jan 14, 2026
Jan 14, 2026
Director of Public Works Peter Petersen presented a quote from Wi Pump Works to replace a pump at Lift Station 2 (installed in 2003); the commission asked staff to return next month with one or two additional quotes before approving purchase.
The full story
Director of Public Works Peter Petersen presented a bid from Wi Pump Works for a replacement pump for Lift Station 2; the minutes note the existing pump was installed in 2003 and is currently functioning but will require replacement eventually. Commissioners agreed the price may rise if replacement is delayed and requested Peter return next month with one or two additional quotes to ensure cost competitiveness.