Project manager reports pay requests, line installation progress and a change order

Jul 14, 2026

Project manager Steve Dachin told the board partial pay requests are moving through — request #8 (~$159,000) and request #9 ($537,000) — reported 15‑inch and 8‑inch PVC installation and said change order #2 (about $66,001.76) was submitted for additional stubs and electrical work; he recommended negotiating an extension to October due to weather delays.

The full story

Steve Dachin provided a project update focused on financial and construction progress. He said partial pay request #8 (approximately $159,000) is in process and partial pay request #9 in the amount of $537,000 was submitted on June 30. He reported installation of 15‑inch and 8‑inch PVC gravity main and that line testing is complete at portions of the project.