Grayson County reviews draft policy to require special-use permits for data centers

Sep 10, 2026

County staff presented a draft data center policy that would define 'Data Center' as a distinct use and require a Special Use Permit in the Industrial (I) zoning district. The draft lists criteria including economic analysis, proof of utility capacity at applicant expense, and mitigation measures for noise, lighting, and visual impacts.

The full story

County Administrator Stephen A. Boyer presented a draft policy addendum proposing to classify data centers as a distinct use subject to Special Use Permit review in the Industrial (I) district. The draft says data centers can strain local utilities — noting Virginia hosts the largest concentration of data-center capacity in the world and that, as drafted, data centers account for roughly one-quarter of the Commonwealth’s electricity consumption, a share projected to approach nearly half by 2030.