County approves Secondary Roads Five‑Year Program; engineer reports ongoing culvert and bridge work

Apr 7, 2025

Engineer Jared Johnson updated the board on roadwork including a completed culvert replacement, ditch clearing, and ongoing bridge and culvert construction at the Tingley 27 site; the board approved the secondary roads County Five‑Year Program (RC25_64).

The full story

Engineer Jared Johnson reported spot rock hauling, bridge rail repairs on Athens 12, sign repair and replacement work, and completion of work order W.O. 1331 (24" ADS culvert replacement). Johnson described ongoing work at the Tingley 27 bridge site, including site clearing, bridge removal and excavation for precast box culvert installation.