Decatur council hears near-complete update on USDA water and wastewater projects

Nov 3, 2025

Wightman engineer Andrew Rudd told council the Drinking Water Improvements Contract A is 98% complete and expected to finish by month’s end; Wastewater Contract B includes underground electrical work at lagoons for groundwater-monitoring pumps.

The full story

Andrew Rudd of Wightman updated the Village Council on USDA-funded water projects, saying the Drinking Water Improvements, Contract A, is 98% complete and "Project should be 100% complete by the end of the month." He said street signs related to the work are scheduled to be installed at the end of the week.