County staff reviewed the research park master plan and infrastructure: about 5 megawatts of available power, broadband by the Eastern Shore of Virginia Broadband Authority, and water/sewer through NASA; Rocket Lab remains the park's only current tenant and taxiway access shapes parcel values and access needs.

The full story

County staff presented the most recent conceptual master plan and described existing utilities and infrastructure constraints at the Wallace Research Park. "As far as Anak is concerned, they mentioned that 5 megawatts is available for power," Lee Hammond told the council while also noting that broadband is provided by the Eastern Shore of Virginia Broadband Authority and that water and sewer service is routed through NASA with the county acting as intermediary.