Bond update: construction advancing; contingencies largely steady

Oct 13, 2026

District bond manager reported progress on CTE and commons footings, a pending slab pour, steel deliveries and a target to fully enclose the high school by January; elementary and HVAC contingencies remain, respectively, about $185,000 over and just under $900,000.

The full story

Mister Williams presented an updated bond status report, telling the board that construction crews are pouring footings for the CTE addition and will move on to the commons footings, with a slab pour expected "sometime this week" and steel arriving later in the month. He said the district hopes to have the project fully enclosed by January, weather permitting.