CDD reviews long-range gatehouse plan; backup irrigation well near completion

Apr 28, 2026

Board reviewed revised Long Range Plan including a completed traffic-calming project, a near-complete backup irrigation well costing $291,500, monument and gatehouse cost estimates and a projected $2.5 million CIP loan to cover revised project timing.

The full story

Board members reviewed a revised Long Range Plan for Pelican Sound gatehouse and neighborhood monument work. Eric Long said the Traffic Calming Project (radar sign and traffic camera) was completed at a cost of $26,739, and that a backup irrigation well—estimated at $291,500—is near completion; Long expects the current pump to be installed and operational within weeks.