San Rafael to ask council to consider progressive design‑build contract Nov. 2 for Albert Park project

Oct 19, 2026

City staff recommended a progressive design‑build delivery method and will bring a recommended contractor/architect team (Excel Construction with SOM) to council on Nov. 2; staff outlined a conceptual design period through June and a target to begin construction in 2028.

The full story

City staff told trustees and commissioners that the project will use a progressive design‑build delivery method, which brings the architect and contractor on as a team early to collaborate on design and cost. Catherine Kufa said the city received eight proposals, interviewed three teams and is recommending a team led by Excel Construction with Skidmore, Owings & Merrill for council consideration on Nov. 2.