Planning board extends 3–15 Ridge Road site‑plan approval by one year after debate
Mar 24, 2026
After discussion about DOT delays and rising costs, the board voted 6–1 to extend site‑plan approval for 3–15 Ridge Road by one year; members said substantial design changes would require new review.
The full story
The Lansing Planning Board voted to extend the site‑plan approval for 3–15 Ridge Road by one year, after hearing from the applicant that delays related to state DOT permitting and signal‑upgrade requirements had cost roughly one building season. The original approval dated 03/27/2023 was set to expire 03/27/2026; the applicant asked for a multi‑year extension and the board ultimately approved a one‑year extension.
Applicant representative (S8) described lengthy DOT review, the need to replace signal electronics and detection equipment, and a rebidding process that pushed the schedule back and increased estimated costs "40%" in the time since the original approval. Chair (S2) and several members said they were reluctant to grant a three‑year extension without clearer evidence of progress, and one member (S4/John LaCitra) registered a no vote. The roll call recorded the following votes: Tom Butler — yes; Sandy Conlon — yes; Althea Riley — yes; Christine Haas — yes; Daniel Hakanimi — yes; John LaCitra — no; Dean Shea — yes. The motion passed 6–1.
Board members asked the applicant to return with a side‑by‑side comparison: the 2023 approved plans versus any proposed revisions, so the board can determine whether changes would be minor or substantial. If changes are substantial, the board said, the applicant must submit a new site‑plan application and return for review.
Written with AI from the event video and transcript. Check it against the source ↓