Committee presses contractor for a usable CPM baseline after delayed earthwork start

Oct 20, 2026

Committee members said earthwork start is later than planned, foundation work now shown in November, and staff urged submission of a CPM‑capable baseline; the contractor supplied Microsoft Project files but staff want clarified logic to ensure critical‑path accuracy.

The full story

Members expressed concern that earthwork start slipped and that foundation work is now pushed into November, a less favorable time to pour foundations.