Drainage projects active across River Ridge; work on four sites expected to finish by end of July
Jun 23, 2026
Jun 23, 2026
District engineer reported four drainage sites are under construction with pipe installation and grading underway; sod and pipe schedules, tree removals and contingency repairs were outlined, and staff will log extra costs for inclusion on the next agenda.
The full story
District Engineer Charlie Krebs told the River Ridge Board that all four drainage-improvement sites are under construction, with sites cleared, silt fences installed and pipe being placed in the ground. He said grading and fill dirt had been completed in Turnberry and that Palmetto Dunes was expected to be finished by the end of the week; if grading continues on schedule the overall project is expected to be completed by the end of July.