Board reviews drainage improvements; Change Order #2 ($6,353.12) distributed

Jul 28, 2026

District staff updated the Board on drainage work across multiple neighborhoods, noting Clarke Construction is the primary contractor, Turnberry work nearing completion, and a Change Order #2 in the amount of $6,353.12 was distributed and discussed; the original bid included a roughly $112,000 contingency.

The full story

District Engineer Charlie Krebs and staff updated the Board on ongoing drainage improvements. Mr. Krebs said Clarke Construction is performing much of the work and reported Turnberry is nearly complete; Palmetto Dunes and Sound III work is done and sodding is in progress in Oak Run, where rain has delayed installation.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in