Consultant outlines WWTP clarifier replacement schedule, financing timeline
Aug 13, 2026
Aug 13, 2026
Ruekert & Mielke reported a schedule for the WWTP Clarifier Replacement Project: bid review completed in July; contract awarded Aug. 7, 2026; loan closing expected Oct. 2026; construction Oct/Nov 2026 start; completion Nov/Dec 2027 on a 400‑day contract.
The full story
Don Heikkila of Ruekert & Mielke presented the schedule for the WWTP Clarifier Replacement Project and summarized key dates: bid review completed in July; contract award on August 7, 2026; an executed contract in August 2026; loan closing targeted for October 2026; construction start in October/November 2026; and construction completion expected in November/December 2027 on a 400‑day contract timeline.