Local utility says data centers must pay their infrastructure share to avoid rate impacts
Oct 7, 2026
Oct 7, 2026
Yampa Valley Electric told Moffat County residents that large, continuous data‑center loads require new rate design or upfront contributions so the cooperative’s general membership is not left covering infrastructure costs.
The full story
At a Moffat County information session, Scott Blecki, president and CEO of Yampa Valley Electric, told residents the cooperative is preparing rate and tariff approaches to prevent residential customers from absorbing costs caused by large data‑center loads. Blecki said data centers are a "24/7 kind of around the clock" load and typically require generation and transmission investments that should be allocated to the load creator, not distributed across all members.