Board amends Merchant Square phase‑2 authorization to $15.6M after contingency adjustment
Oct 20, 2026
Oct 20, 2026
Officials described replacing roughly 8,000 linear feet of sewer main (upsizing 12" to 18") and about 2,600 linear feet of water main in Merchant Square; the board amended and approved the total authorization to $15,607,150 after discussing owner contingency and a roughly $85,000 change.
The full story
Lane Young, director of utilities, presented the Merchant Square phase‑2 scope: roughly 8,000 linear feet of sewer replacement (upsizing from 12" to 18") and about 2,600 linear feet of water main replacement, much of it deep (around 25 feet). The project carries complexity because of depth and routing through Medical Drive, AAA Way, and Keystone Way.