Riley County approves temporary transfer‑station plan during tipping‑floor construction

Jan 23, 2026

County public works presented two options for the transfer station during construction; commissioners approved a temporary operation plan that staff and KDHE support, with equipment costs estimated at $40,000–$60,000 versus closure costs of about $34,000–$35,000.

The full story

Riley County approved a temporary operation plan Jan. 22 to keep the county transfer station open while a new tipping floor is built. Public works director Evan McMillan told the board the county has two options: close the transfer station for the estimated two‑month construction window (cost to county roughly $34,000–$35,000 in salaries/overhead), or stay open under a temporary configuration that would require additional equipment and traffic controls with estimated equipment/material costs of "anywhere from 40,000 to 60,000 just on equipment."