Design team outlines phased construction approach; supervisors asked about temporary relocation options

Oct 15, 2026

Designers proposed phasing beginning around the server room, then moving IT to allow subsequent phases; supervisors asked about temporary trailers, Pinecrest space and courthouse rooms for displaced staff while warning that more phases raise cost and duration.

The full story

Envision presented a likely phasing plan that would start with work around the existing server room, move IT across the hall, then complete supervisor-side renovations. The team warned that additional phases raise both cost and duration and emphasized the need to identify temporary work locations for displaced staff.