The Department of Public Works reported construction progress—foundations, piers and temporary power in place—and said the project experienced three theft incidents. DPW is working with the Tompkins County Sheriff's Department and recommends improved camera systems and other security measures.

The full story

The Department of Public Works updated the board on progress at the Town Barn construction site and on recent security incidents.

Mikey (DPW) told the board that CMU foundations and piers are complete, temporary power has been installed with NYSEG, exterior siding work was expected to begin around 01/26/2026, and steel delivery was targeted for about 01/23/2026 (subject to weather). He reported three thefts at the project site — two break-ins of tool boxes and one incident of gas theft — and said the department is coordinating with the Tompkins County Sheriff's Department and evaluating camera and metering improvements to deter future thefts.

Mikey said the contractor has been accommodating some increased heating costs and that the town is reviewing contract language on change orders. He thanked crews for winter maintenance work and asked for any questions.

Provenance: topicintro SEG 087, topfinish SEG 196

Written with AI from the event video and transcript. Check it against the source ↓