Circle Park work progressing; on-site walkthrough set for March 26

Mar 18, 2025

Town staff reported positive site-visit findings for Circle Park (footer rock placement and ramp walls) and a contractor-provided timeline that targets substantial completion by the end of June; an on-site walkthrough with the project foreman is scheduled for March 26 at 4:00 p.m.

The full story

Administrator Etheridge reported positive technical findings from Michael Scurlock regarding Circle Park site visits, including footer rock placement and ramp wall installation. Etheridge said contractor Jake Haskins provided an updated timeline: finish low-level riverbank stabilization and access work in the next couple of weeks, pause during high water in April, then resume work with "substantial completion by the end of June." An on-site walkthrough with project foreman Pete Seewald was scheduled for Wednesday, March 26 at 4:00 p.m.