Change order returns $71,426.12 to county from Sheriff's Detention Dorm project

Oct 14, 2026

A deductive change order with RD Brown Contractors for phase 2 of the Sheriff's Detention Dorm was presented and approved; the project came in under budget and the county will receive $71,426.12 back, per staff.

The full story

A staff presenter described a deductive change order with RD Brown Contractors for phase 2 of the Sheriff's Detention Dorm project (a 1722 SPLAS project). The project was under the construction budget and the county will receive $71,426.12 back as final accounting for the phase.