Courthouse elevator punch list declared complete but final payment held pending county walk-through
Oct 6, 2026
TCS Northwest and Slate Architecture said physical punch-list work on the courthouse elevator was complete; the county will withhold final payment until it completes a walk-through and reviews updated punch-list documentation and photos.
The full story
Representatives from TCS Northwest and Slate Architecture reported that the physical punch-list work on Granite County's courthouse elevator was complete, but county officials deferred final payment until internal inspection and documentation review.
TCS agreed to provide an updated punch-list and photographs; Slate Architecture said it would review that documentation. Commissioner Adler said he planned a walkthrough after the meeting and the board emphasized the need to coordinate construction work around court schedules and the judge's directions to stop work when necessary. The county did not authorize final payment at the meeting.
The discussion also covered roof-access windows; the architect said replacement windows would generally match existing sizes, with one narrower window near the elevator wall. Commission and counsel noted construction scheduling must avoid disruption of court proceedings.