Board approves $5.5M construction documents for Building 800 HVAC, lighting and fire-alarm work

Oct 21, 2026

Facilities staff recommended using a CMAR procurement for a Building 800 project—HVAC replacement, lighting retrofit and a new fire alarm—with a budget of $5,500,000 from 2023 bond funds; trustees approved the documents and procurement method.

The full story

Thomas, the facilities presenter, told trustees the district is bringing 100% construction documents and a procurement recommendation for Building 800: "What we will be going to the CMR to bid on is a $5,500,000 budget." He said the work includes HVAC replacement, a full-building lighting retrofit and a new fire-alarm system; staff recommended a Construction Manager at Risk (CMAR) procurement because the campus will be active during the work and phasing control is needed.