Board hears progress report on drainage improvements; trees to be removed and replanted
Jun 23, 2026
Jun 23, 2026
District Engineer reported all four drainage sites are under construction with expected completion by end of July if grading finishes; 12 trees in Palmetto Dunes and six Cabbage Palms in Oak Run will be removed and replaced.
The full story
The River Ridge Board received a construction update on drainage improvements on June 23. Charlie Krebs reported that all four sites are under construction, silt fences are installed and fill is staged at Turnberry; Palmetto Dunes sod work is expected the week of July 2 and pipe installation in Oak Run the week of June 29. If grading is completed, the project is expected to finish by the end of July.