Courthouse project update: scaffolding, lightning protection and ice‑guard pricing requested
Oct 21, 2026
Oct 21, 2026
Officials updated the board on courthouse construction sequencing—steel and scaffolding installation, lightning‑protection routing and a request for pricing on ice guards to prevent hazardous sliding ice around the courthouse entrance; change orders above $75,000 were flagged as requiring reconvening the board.
The full story
A committee member reviewed the courthouse construction schedule, telling the board that steel would be erected and scaffolding placed soon and that the team intends to mount blocking under the roof rather than cut holes through it. The member described the work sequence and emphasized lightning protection routing and the planned spire replacement.