Engineering updates: ROW progress, change orders and bid schedule adjustments

Feb 24, 2026

Engineering reported Phase 2 had 30 of 34 right-of-ways (ROWs) secured with outstanding ROWs from two businesses, one utility and one resident; vendor bid opening for Chub Run was moved from Feb. 24 to March 10, 2026; multiple change orders and amendments were presented for Phase 1 and Chub Run.

The full story

Town engineering staff presented updates across multiple projects. For Phase 2 AMD work staff reported 30 of 34 ROWs are in hand; they continue to pursue ROWs from two businesses, one utility and one resident and noted the Department of Health permit is under review. For Phase 1 the council was presented with Change Order 4, Engineering Amendment 2 and a Notice of Acceptability. Chub Run items included review of progress meeting minutes and presentation of Change Orders 1 and 2. The vendor bid opening for Chub Run was rescheduled from Feb. 24 to March 10, 2026. Phase IV remains waiting on contractor remobilization.