Shell Mound dredging delayed as contractor, DEP discuss dewatering method
Oct 20, 2026
Engineering staff said the Shell Mound dredge contractor's alternative dewatering method failed; the county issued a 90‑day no-cost time extension and is working with DEP and the contractor on permit changes and a demobilization plan so another boat ramp can proceed while Shell Mound pauses.
The full story
County engineers updated the board on the Shell Mound dredging project, reporting the contractor’s dewatering approach failed and that staff are working with the contractor and the Florida Department of Environmental Protection to identify an acceptable method.