Public Works reports Highway 92 ADA work, pond pumping and SCADA connectivity progress

Jul 28, 2025

Trustee Dan Olson reported the start of ADA crosswalk work tied to Highway 92 and related mill-and-overlay scheduling, noted Lincoln Street pond pumping and water-safety sampling, and said crews addressed intermittent SCADA connectivity after a recent internet change at the treatment plant.

The full story

Trustee Dan Olson told the board county crews have begun ADA crosswalk work related to Highway 92 and that Brooklyn’s work will be scheduled to avoid a planned concert. He said the project team is coordinating mill-and-overlay timing with the county to minimize disruption to local events.