County reports progress on HVAC, elevators, coroner lab and parking projects

Aug 19, 2026

The director of building and grounds updated commissioners on several capital projects: admin HVAC phase 1 is complete, rooftop HVAC work is scheduled for mid-September, elevator parts delays push courthouse work to early September and JJC work to year-end, and the coroner's autopsy lab is expected to finish in early November.

The full story

Jeff Fuller, director of building and grounds, briefed the board on multiple capital projects on Aug. 18, reporting several completions, near-term schedules, and items needing follow-up.

Fuller said phase 1 of the admin HVAC replacement — 72 terminal units in ceiling grids — is complete and rooftop work (phase 2) is being scheduled for mid-September; that work will require 2–3 crane lifts and render the building without heating or cooling for 3–4 weeks. He said notices will be issued as the schedule firms up and staff is monitoring weather to avoid hot afternoons during the outage.

Elevator-work timelines were updated: the admin building elevator work is finished, but courthouse elevator work was delayed when two components did not ship; Fuller expects those parts in early September. The Juvenile Justice Center elevator parts are expected late in the year with work to follow in December–January.

Other completed or near-complete items include parking-lot resealing (contractor to finish small remaining spots and striping), a completed generator and gel pod expansion, and substantial progress on gel HVAC phase 1. Fuller said coroner's autopsy-lab under-slab plumbing and framing work are mostly complete and that the project should be finished in the first week of November.

Fuller asked commissioners whether they had questions about timing and confirmed he will return with notices and any additional scheduling information; the board accepted the update and gave direction where needed.