Council notes small contract reduction after South 3rd Avenue inspection
Oct 21, 2026
A change order for the South 3rd Avenue water-main and sewer/lighting project reduced the contract by $2,550 after inspection showed a service line at 23 South 3rd did not need replacement; the item was included on the agenda and appears in the consent agenda.
The full story
Matthew Hirsch, chair of the Public Works and Public Utilities Committee, told the council that the borough had originally awarded a change order in August for approximately $345,000 for the South 3rd Avenue water-main replacement, sewer main cleaning and lighting project. Following inspection, staff determined that the water service line at 23 South 3rd Avenue did not need to be replaced, reducing the contract by $2,550.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →