Matthew Hirsch, chair of the Public Works and Public Utilities Committee, told the council that the borough had originally awarded a change order in August for approximately $345,000 for the South 3rd Avenue water-main replacement, sewer main cleaning and lighting project. Following inspection, staff determined that the water service line at 23 South 3rd Avenue did not need to be replaced, reducing the contract by $2,550.