Utilities tell FERC: outage windows, queue uncertainty and communications hinder safe integration of large loads

Oct 21, 2026

Utility panelists from Dominion, SRP, PJM and others told FERC that the biggest practical barriers to connecting large computational loads are limited outage availability for construction, uncertain queues and permitting, and a need for automation/operational desks and enforceable contractual terms to coordinate flexible responses.

The full story

Utility speakers described on-the-ground operational challenges in connecting very large loads. Brian Starling (Dominion Energy) said outage availability for construction—taking existing elements out of service to add new lines or equipment—has become a critical bottleneck: "we're almost to a point now where we can't take these elements out of service anymore." SRP described a large‑customer cluster process and showed that deposit and commitment requirements can dramatically shrink speculative queues: SRP studied 24 customers representing 7.2 GW of prospective load and, after upfront cost estimates and commitments, the queue decreased to roughly 900 MW.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in